DSCO provided Testing & Commissioning Consultancy for NTT’s Greenfield Data Centre of approximately 27,000 sqm with 13,500kW of IT Load in 9 data halls by conducting a Site Acceptance Test and Integrated Systems Test Services.

NTT communications opened Phase 1 of the new Hong Kong Financial Data Centre (FDCTM) in Tseung Kwan O Industrial Estate with over 80% of Phase 1 capacity in the new Data Centre was reserved prior to launch. It will incumbent on the firm to ensure that the design, function and quality of all MEPF services are value-added. Of primary concern is the reliability of the MEPF systems to suit this critical facility. Secondary inter-related matters that will be considered will be local regulations, energy and re-current costs, buildability, maintainability, flexibility and redundancy.

The Tier IV ready facility boasts a 100% uptime service level, unrivalled security, connection to NT’s ultra-low latency networks and close proximity to the data centre operations of regional exchanges.

No description available...